How to renovate an apartment before renting it - a complete guide
Planning and implementation of the reconstruction of an investment apartment. Budget, priorities, materials, craftsmen and return on investment.
Introduction to renovation for rent
Renovation of an apartment before renting is a strategic decision that can significantly affect the profitability of your investment. A properly executed renovation will increase rents, attract quality tenants and reduce maintenance costs. In this article, we will show you how to plan, implement and maximize the benefit of the renovation.
Unlike the renovation of your own home, where personal preferences decide, with an investment apartment you have to think pragmatically: which investment will bring the highest return.
Decision on renovation
When to renovate
Signals for renovation:
- Outdated disposition (transient rooms)
- Old installations (original wiring)
- Inadequate bathroom and kitchen
- Low energy standard
- Problems with rent
When you do not need to renovate:
- The apartment is in good condition
- The target group does not require a high standard
- The costs would not bring about a corresponding increase in rent
- The location does not allow for higher rent
Types reconstruction
Complete reconstruction:
- New installations (water, electricity, heating)
- New floors and surfaces
- New bathroom and kitchen
- Change of layout
- Costs: 15,000-30,000 Kč/m²
Partial reconstruction:
- Preservation of installations
- New surfaces and painting
- Bathroom and kitchen modernization
- Costs: Kč 5,000-15,000/m²
Cosmetic finishing:
- Painting
- Minor repairs
- Floor replacement
- Costs: Kč 1,000-5,000/m²
Planning and budget
Budgeting
Rule 1-3%: Annual maintenance and improvement costs should not exceed 1-3% of the value of the property.
Calculation of return:
- Rent increase after reconstruction: 3,000 Kč/month
- Annual benefit: 36,000 Kč
- Investment: 300,000 Kč
- Return: 300,000 / 36,000 = 8.3 years
Recommended return:
- Ideal: 3-5 years
- Acceptable: 5-8 years
- Risky: over 8 years
Investment priorities
Sorted by return:
1. Bathroom (highest priority)
- Key to tenant decision-making
- High impact on rent
- Payback: 3-5 years
2. Kitchen
- The second most important room
- Functionality and aesthetics
- Payback: 4-6 years
3. Floors
- Great visual impact
- Long service life
- Payback: 5-8 years
4. Windows
- Energy savings
- Comfort and aesthetics
- Payback: 8-12 years
5. Disposition
- Intervention in load-bearing structures
- High costs
- Payback: individual
Budget reserve
Always count on a reserve of 10-20% for unforeseen expenses:
- Hidden defects
- Changes in the project
- Extension of deadlines
Selection of materials
Criteria for rental
Resistance:
- High load from changing tenants
- Easy to repair
- Long service life
Maintenance:
- Easy cleaning
- Scratch resistance
- Time consuming maintenance
Neutrality:
- Universal appearance
- Unlimited time design
- Wide acceptability
Recommended materials
Floors:
- Vinyl tiles (LVT): 500-1,000 Kč/m²
- Laminate: 300-600 Kč/m²
- Ceramic tiles (wet areas): 400-800 Kč/m²
Walls:
- Washable paints: 100-200 Kč/m²
- Ceramic tiles (bathroom, kitchen): 400-800 Kč/m²
Kitchen:
- Laminate line: 30,000-60,000 Kč
- Laminate worktop: 1 000-2,000 Kč/bm
- Basic appliances: 30,000-50,000 Kč
Bathroom:
- Sanitary ceramics (middle class): 15,000-30,000 Kč
- Batteries: 3,000-6,000 Kč
- Shower: 5,000-15 Kč 000
Materials to avoid
- Carpet (unhygienic, demanding maintenance)
- Wooden parquets (susceptible to damage)
- Luxury materials (do not match the rent)
- Trendy colors (quickly outdated)
Realization of reconstruction
of craftsmen
Options:
- General contractor (manages everything)
- Individual craftsmen (you coordinate yourself)
- Combination (key work professionals, others yourself)
Selection of supplier:
- References and portfolio
- Written contract
- Time schedule
- Warranty conditions
Work schedule
Typical complete reconstruction procedure:
Week 1-2: Preparation
- Clearing the apartment
- Demolition work
- Debris removal
Week 3-4: Installation
- Electrical installation
- Plumbing
- Heating
Week 5-6: Rough Work
- Plastering and Leveling
- Ceilings
- Floor Preparation
Week 7-8: Tiling
- Bathroom
- Kitchen
- Wet Floors
Week 9-10: Flooring and Painting
- Floating Floors
- Painting
- Doors
Week 11-12: Completion
- Kitchenline
- Plumbing
- Cleaning and Finishing
Quality Control
In-progress Checks:
- Concealed Piping Before Covering
- Bathroom Drops
- Levelness surfaces
Final acceptance:
- Functionality of all devices
- Visual inspection
- List of defects to be removed
- Handover protocol
Apartment equipment
Basic equipment
Standard equipment:
- Kitchen line with sink
- Hob and oven
- Hood
- Boiler or boiler
- Sanitary equipment
Superior equipment:
- Dishwasher
- Washing machine
- Refrigerator
- Microwave oven
Furniture
Unfurnished apartment:
- Lower rent
- Less maintenance
- Wider target group
Furnished flat:
- Higher rent (+15-25 %)
- Young professionals, expats
- Higher wear and tear
- Need to change
Partly furnished:
- Compromise
- Kitchen + built-in wardrobes
- No free furniture
Specifics for rent
Installation in addition
Security:
- Safety lock
- Peephole and chain
- Smoke detectors
Practicality:
- Sufficient sockets
- USB sockets
- Quality WiFi wiring
Economy:
- Thermostatic heads
- LED lighting
- Energy-saving batteries
Design and colors
Recommended:
- White walls
- Light neutral colors
- Minimalist design
- Quality basic equipment
Not recommended:
- Bold colors
- Patterned wallpapers
- Complicated solutions
- Cheap imitation
Examples of renovations
Example 1: Cosmetic renovation
Apartment 2+kk, 50 m²:
- Painting: 15,000 Kč
- Laminate floors: 25,000 Kč
- Minor repairs: 10,000 Kč
- Total: 50,000 Kč
- Rent increase: 1,500 Kč/month
- Payback: 2.8 years
Example 2: Partial reconstruction
Apartment 2+kk, 50 m²:
- New bathroom: Kč 120,000
- New kitchen: Kč 80,000
- Floors and painting: Kč 50,000
- Total: Kč 250,000
- Rent increase: Kč 4,000/month
- Payback: 5.2 years
Example 3: Complete reconstruction
Apartment 2+kk, 50 m²:
- Demolition and preparation: Kč 50,000
- Installation: Kč 150,000
- Bathroom: Kč 150,000
- Kitchen: Kč 120,000
- Floors and surfaces: Kč 100,000
- Doors and accessories: Kč 50,000
- Total: Kč 620,000
- Rent increase: Kč 6,000/month
- Payback: 8.6 years
Tax aspects
Deductible costs
Repairs and maintenance:
- Fully deductible in the year of creation
- They do not increase the value of the property
Technical evaluation:
- Above 80,000 Kč/year
- Depreciated gradually (30 years)
- Increases the value of the property
Strategic planning
- Spread the work into more years (under Kč 80,000)
- Separate repairs from technical evaluation
- Consult a tax advisor
Conclusion
Successful renovation for rental requires:
- Analysis - is the investment in the given location worth it?
- Planning - realistic budget and schedule
- Correct priorities - bathroom and kitchen first
- Practical materials - resistance to luxury
- Quality implementation - reliable craftsmen
- Neutral design - universal taste
Reconstruction is an investment that should bring a measurable return. Make decisions based on numbers, not emotions, and your investment will return in the form of higher rents and happier tenants.
> Czech-law scope and editorial note: Legal, tax, accounting, tenancy, service-charge, condominium, metrology, insurance and data-protection statements in this article refer to the Czech Republic and the rules effective for the relevant date. Figures and examples are illustrative, not legal or tax advice. Verify current rules with the relevant Czech authority or a qualified adviser.